As the project progresses, the actual finish times (AFs) of completed activities will determine
 a. the earliest start and earliest finish times for the remaining activities in the network diagram, as well as the total slack.
  b. the earliest start and earliest finish times for the completed activities in the network diagram, as well as the total slack.
  c. the latest start and latest finish times for the remaining activities in the network diagram, as well as the total slack.
  d. the latest start and latest finish times for the completed activities in the network diagram, as well as the total slack.
Read 33 times
1 Reply
Replies
Answer verified by a subject expert
lightingmcqueenlightingmcqueen
wrote...
Top Poster
Posts: 911
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Micky5490! Author
wrote...

6 years ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

Yesterday
Helped a lot
wrote...

2 hours ago
You make an excellent tutor!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  849 People Browsing
Related Images
  
 187
  
 979
  
 52
Your Opinion
Which 'study break' activity do you find most distracting?
Votes: 820