A government was billed $3,000,000 during the year on its capital project, of which $2,700,000 was paid. The total contracted cost is $5,200,000. The government does not plan to pay the $300,000 balance currently owed to the contractor until the project has been completed and approved. The government should report Capital Projects Fund expenditures for the current year equal to
A.   $2,700,000.
B.   $3,000,000.
C.   $4,900,000.
D.   $5,200,000.
Read 478 times
3 Replies
Diesel
Replies
Answer accepted by topic starter
f_zah1f_zah1
wrote...
Top Poster
Posts: 10774
9 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

goji.go Author
wrote...
9 years ago
Thanks so much f_zah1.

You were correct Smiling Face with Open Mouth
Diesel
wrote...
9 years ago
You're very welcome!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1312 People Browsing
Related Images
  
 908
  
 607
  
 968
Your Opinion
Where do you get your textbooks?
Votes: 372