The critical path in a PERT diagram is the one that:
 
  A) has the most activities on it.
 
  B) has activities that can be delayed and not impact the completion date of the project.
 
  C) takes the longest amount of time.
 
  D) is the most likely to occur.
Read 36 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
C