The diagram below shows the activities on the nodes, and the table shows the normal time and crash time (in days) and cost for each activity.



ActivityNormal TimeCrash TimeCost per day to crash
A66---
B108$100
C54$300
D41$700
E97$500
F21$650

Which activity should be crashed to reduce the project completion time by one day?

• E

• B

• C

• D
Textbook 
Introduction to Management Science

Introduction to Management Science


Edition: 13th
Author:
Read 85 times
1 Reply
Replies
Answer verified by a subject expert
ZanLauZanLau
wrote...
Posts: 200
5 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here

Related Topics

orengo Author
wrote...

5 years ago
You make an excellent tutor!
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Brilliant
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  967 People Browsing
Related Images
  
 311
  
 1108
  
 295
Your Opinion
Which country would you like to visit for its food?
Votes: 204