The Maxit Corporation has a standard costing system in which variable manufacturing overhead is assigned to production on the basis of standard machine-hours. The following data are available for July:

  • Actual variable manufacturing overhead cost incurred: $23,060
  • Actual machine-hours worked: 1,800 hours
  • Variable overhead rate variance: $3,720 U
  • Total variable overhead spending variance: $5,060 U

The variable overhead efficiency variance for July is:



▸ $1,340 U

▸ $8,780 U

▸ $8,780 F

▸ $1,340 F
Textbook 
Introduction to Managerial Accounting: Brewer Edition: 9e

Introduction to Managerial Accounting: Brewer Edition: 9e


Edition: 9th
Authors:
Read 37 times
1 Reply
Replies
Answer verified by a subject expert
kady_kelsey2kady_kelsey2
wrote...
Posts: 155
Rep: 0 0
11 months ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

sanimkyei Author
wrote...

11 months ago
You make an excellent tutor!
wrote...

Yesterday
this is exactly what I needed
wrote...

2 hours ago
Helped a lot
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1344 People Browsing
Related Images
  
 1120
  
 829
  
 3138
Your Opinion
Who's your favorite biologist?
Votes: 586