silverbullet silverbullet
wrote...
Posts: 2784
Rep: 2 0
8 years ago
The single milling machine at Stout Manufacturing was severely overloaded last year. The plant operates eight hours per day, five days per week, and 50 weeks per year. Management prefers a capacity cushion of 15 percent. Two major types of products are routed through the milling machine. The annual demand for product A is 3000 units and 2000 units for product B. The batch size for A is 20 units and 40 units for B. The standard processing time for A is 0.5 hours/unit and 0.8 for B. The standard setup time for product A is 2 hours and 8 hours for product B. How many new milling machines are required if Stout does not resort to any short-term capacity options?
A) No new machines
B) 3 or 4 new machines
C) 1 or 2 new machines
D) More than 4 new machines
Textbook 
Operations Management: Processes and Supply Chains

Operations Management: Processes and Supply Chains


Edition: 11th
Authors:
Read 137 times
2 Replies
Replies
Answer verified by a subject expert
GL700WingGL700Wing
wrote...
Top Poster
Posts: 589
8 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

silverbullet Author
wrote...
8 years ago
thanks for being so helpful
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1218 People Browsing
Show Emoticons
:):(;):P:D:|:O:?:nerd:8o:glasses::-):-(:-*O:-D>:-D:o):idea::important::help::error::warning::favorite:
Related Images
  
 216
  
 587
  
 894
Your Opinion
Who's your favorite biologist?
Votes: 743