Barry's Tire Service completed 100 tire changes, six brake jobs, and 16 alignments in an eight-hour day with his standard crew of six mechanics. A brake specialist costs $16 per hour, a tire changer costs $8 per hour, and an alignment mechanic costs $14 per hour. The materials cost for a day was $2000, and overhead cost was $500.
a.   What is the shop's labor productivity if the retail price for each respective service is $60, $150, and $40?
b.   What is the multifactor productivity, if the crew consisted of two of each type mechanic?
Read 2126 times
1 Reply

Related Topics

Replies
wrote...
Educator
7 years ago
a.   ((100 × 60 + 6 × 150 + 16 × 40)/6 × 8) = $157/hr

b.   ({(100 × 60) + (6 × 150) + (60 × 40)}/{(2 × 8 × 16) + (2 × 8 × 8) + (2 × 8 × 14) + 2000 + 500}) = 2.43
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1283 People Browsing
Related Images
  
 387
  
 112
  
 341
Your Opinion
Which industry do you think artificial intelligence (AI) will impact the most?
Votes: 352