mjhgfd mjhgfd
wrote...
6 years ago
A key for developing project cost estimates is to:
 
  A) Cost the project while considering the total package.
  B) Cost the project on a work package and task basis.
  C) Cost the project on a major module basis.
  D) Cost the project and add 33 for contingency.
Read 93 times
2 Replies
Replies
Answer verified by a subject expert
Beka128Beka128
wrote...
Top Poster
Posts: 919
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free