× Didn't find what you were looking for? Ask a question
Top Posters
Since Sunday
5
a
5
k
5
c
5
B
5
l
5
C
4
s
4
a
4
t
4
i
4
r
4
New Topic  
ruskin ruskin
wrote...
Posts: 664
6 years ago
Which of the following is NOT a component in a materials requirement planning system?
A) lead times of all items to be purchased
B) master production schedule
C) bill of materials filed
D) standard construction times for all components produced externally
E) demand forecasts for finished goods
Textbook 
Cost Accounting: A Managerial Emphasis, Canadian Edition

Cost Accounting: A Managerial Emphasis, Canadian Edition


Edition: 7th
Authors:
Read 43 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
D
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1211 People Browsing
Related Images
  
 179
  
 309
  
 298
Your Opinion
Who's your favorite biologist?
Votes: 586