Top Posters
Since Sunday
t
7
m
6
k
6
F
5
j
5
t
5
j
5
G
5
f
5
a
5
d
5
c
5
New Topic  
chimeric chimeric
wrote...
Posts: 669
Rep: 0 0
6 years ago
The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?
A) 81.28
B) 92.8
C) 81.82
D) .81954
E) None of the above
Textbook 
Quantitative Analysis for Management

Quantitative Analysis for Management


Edition: 12th
Authors:
Read 75 times
1 Reply
Replies
Answer verified by a subject expert
VitatVitat
wrote...
Posts: 495
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

chimeric Author
wrote...

6 years ago
Thanks for your help!!
wrote...

Yesterday
this is exactly what I needed
wrote...

2 hours ago
Thanks
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  961 People Browsing
Related Images
  
 4442
  
 947
  
 659
Your Opinion
Which industry do you think artificial intelligence (AI) will impact the most?
Votes: 379

Previous poll results: What's your favorite math subject?