The time required to complete a project is known to be normally distributed with a mean of 44 weeks and a standard deviation of 8 weeks.
(a) What is the probability that the project is finished in 40 weeks or fewer?
(b) What is the probability that the project is finished in 52 weeks or fewer?
(c) There is a 95 percent chance that the project will be finished in fewer than how many weeks?
Textbook 
Quantitative Analysis for Management

Quantitative Analysis for Management


Edition: 12th
Authors:
Read 60 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
(a) 0.30854 (b) 0.84135 (c) 44 + 1.645(8) = 57.16
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1350 People Browsing
Related Images
  
 241
  
 137
  
 294
Your Opinion
What percentage of nature vs. nurture dictates human intelligence?
Votes: 431