Which of the following statements about project crashing is false?
A) The crash cost is greater than or equal to the normal cost of an activity.
B) The crash time is less than or equal to the normal time to complete an activity.
C) Reducing the time of an activity on the critical path automatically reduces total project duration.
D) It may not be possible to crash a particular activity.
E) Crashing may not lead to an overall reduction in costs for the project.
Textbook 
Quantitative Analysis for Management

Quantitative Analysis for Management


Edition: 12th
Authors:
Read 55 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
C
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  740 People Browsing
Related Images
  
 388
  
 417
  
 1123
Your Opinion
Which 'study break' activity do you find most distracting?
Votes: 820