× Didn't find what you were looking for? Ask a question
Top Posters
Since Sunday
p
4
h
4
c
4
d
3
3
c
3
t
3
u
3
A
3
B
3
j
3
s
3
New Topic  
Dragon.amg86 Dragon.amg86
wrote...
Posts: 655
Rep: 0 0
6 years ago
Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion.
 
  Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline?
  A) 0.0401
  B) 0.4599
  C) 0.8056
  D) 0.9599
  E) near 1.0000, or almost certain
Read 45 times
1 Reply
Replies
Answer verified by a subject expert
PercymatePercymate
wrote...
Top Poster
Posts: 1205
Rep: 6 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Dragon.amg86 Author
wrote...

6 years ago
this is exactly what I needed
wrote...

Yesterday
Just got PERFECT on my quiz
wrote...

2 hours ago
Thanks
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1137 People Browsing
Related Images
  
 215
  
 2533
  
 456