Dragon.amg86 Dragon.amg86
wrote...
Posts: 655
Rep: 0 0
6 years ago
Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion.
 
  Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline?
  A) 0.0401
  B) 0.4599
  C) 0.8056
  D) 0.9599
  E) near 1.0000, or almost certain
Read 47 times
1 Reply
Replies
Answer verified by a subject expert
PercymatePercymate
wrote...
Top Poster
Posts: 1205
Rep: 6 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Dragon.amg86 Author
wrote...

6 years ago
This helped my grade so much Perfect
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Thanks for your help!!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  425 People Browsing
 134 Signed Up Today
Related Images
  
 648
  
 175
  
 562
Your Opinion
Which 'study break' activity do you find most distracting?
Votes: 824