Which of the following is NOT an assumption of the critical path method?
 a. Activities are independent of one another.
  b. Activity time estimates are stable.
  c. Activity times are characterized by a beta probability distribution.
  d. Once an activity is started, it continues uninterrupted until completion.
Read 34 times
1 Reply
Replies
Answer verified by a subject expert
red r.red r.
wrote...
Top Poster
Posts: 900
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

macgeek312 Author
wrote...

6 years ago
Correct Slight Smile TY
wrote...

Yesterday
this is exactly what I needed
wrote...

2 hours ago
Thanks
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1325 People Browsing
Related Images
  
 422
  
 72
  
 100
Your Opinion

Previous poll results: How often do you eat-out per week?