Which of the following is NOT an assumption of the critical path method?
 a. Activities are independent of one another.
  b. Activity time estimates are stable.
  c. Activity times are characterized by a beta probability distribution.
  d. Once an activity is started, it continues uninterrupted until completion.
Read 37 times
1 Reply
Replies
Answer verified by a subject expert
red r.red r.
wrote...
Top Poster
Posts: 900
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

macgeek312 Author
wrote...

6 years ago
Helped a lot
wrote...

Yesterday
Thank you, thank you, thank you!
wrote...

2 hours ago
Thanks
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  514 People Browsing
Related Images
  
 1977
  
 456
  
 278
Your Opinion
Which is the best fuel for late night cramming?
Votes: 234