All of the following activities are appropriate upon completion of risk response planning EXCEPT:
 a. The risk register should be updated to reflect the risk response strategies.
  b. The risk register should be baselined after planning is completed, and should not be updated once the project is in flight.
  c. The project plan should be updated to reflect any changes to the project schedule, budget or resource assignments.
  d. A single person should be assigned as the owner of each risk.
Read 51 times
1 Reply
Replies
Answer verified by a subject expert
Sammyfuria2Sammyfuria2
wrote...
Top Poster
Posts: 935
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

zhamila Author
wrote...

6 years ago
You make an excellent tutor!
wrote...

Yesterday
Smart ... Thanks!
wrote...

2 hours ago
this is exactly what I needed
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  920 People Browsing
Related Images
  
 265
  
 518
  
 18166
Your Opinion
What percentage of nature vs. nurture dictates human intelligence?
Votes: 432