A project has the activity duration and cost information indicated in the table where all times are in weeks. For every week longer than 30 weeks, there is a penalty of 300.
 
  What is the highest total cost for completing this project?
 
  Activity Normal time Crash time Normal Cost Crash Cost Predecessor
  A 8 5 1,000 2,000
  B 6 4 1,500 2,000 A
  C 8 5 1,800 2,300 A
  D 12 9 1,000 1,800 B
  E 14 11 950 1,450 B
  F 9 7 1,500 1,900 C, D
  G 7 5 2,300 2,800 E, F
  A) 14,250
  B) 13,950
  C) 13,550
  D) 13,150
Read 111 times
2 Replies
Replies
Answer verified by a subject expert
ashxeveashxeve
wrote...
Top Poster
Posts: 917
Rep: 1 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

wrote...
2 years ago
thank you
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1025 People Browsing
 110 Signed Up Today
Related Images
  
 159
  
 618
  
 196
Your Opinion
What's your favorite math subject?
Votes: 293