Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project if the base cost for each activity finished in normal time is 1,000.
 
  Activity Normal Time Minimum Time Crash Cost (/day) Predecessor
  A 10 6 70 --
  B 6 3 40 --
  C 2 2 -- B
  D 4 2 60 C
  E 6 4 80 A
  F 8 5 90 D, E
  A) 400
  B) 420
  C) 440
  D) 460
Read 114 times
1 Reply
Replies
Answer verified by a subject expert
lamaituyalamaituya
wrote...
Top Poster
Posts: 887
Rep: 8 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

madhumeta Author
wrote...

6 years ago
Just got PERFECT on my quiz
wrote...

Yesterday
Thank you, thank you, thank you!
wrote...

2 hours ago
Brilliant
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1687 People Browsing
Related Images
  
 271
  
 311
  
 637
Your Opinion