Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project if the base cost for each activity finished in normal time is 1,000.
 
  Activity Normal Time Minimum Time Crash Cost (/day) Predecessor
  A 10 6 70 --
  B 6 3 40 --
  C 2 2 -- B
  D 4 2 60 C
  E 6 4 80 A
  F 8 5 90 D, E
  A) 400
  B) 420
  C) 440
  D) 460
Read 116 times
1 Reply
Replies
Answer verified by a subject expert
lamaituyalamaituya
wrote...
Top Poster
Posts: 887
Rep: 8 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

madhumeta Author
wrote...

6 years ago
This helped my grade so much Perfect
wrote...

Yesterday
Thanks
wrote...

2 hours ago
this is exactly what I needed
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1533 People Browsing
 105 Signed Up Today
Related Images
  
 271
  
 613
  
 234
Your Opinion
Who will win the 2024 president election?
Votes: 119
Closes: November 4

Previous poll results: Where do you get your textbooks?