A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of 250 per week for every week the project extends beyond 32 weeks.
 
  What is the duration of the least expensive project possible?
 
  Activity Normal time Crash time Normal Cost Crash Cost Predecessor
  A 8 5 1,000 2,000
  B 6 4 1,500 2,000 A
  C 8 5 1,800 2,300 A
  D 12 9 1,000 1,800 B
  E 14 11 950 1,450 B
  F 9 7 1,500 1,900 C, D
  G 7 5 2,300 2,800 E, F
  A) 38 weeks
  B) 37 weeks
  C) 36 weeks
  D) 35 weeks
Read 100 times
1 Reply
Replies
Answer verified by a subject expert
jgfndjgfnd
wrote...
Top Poster
Posts: 871
Rep: 1 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

djnurs1 Author
wrote...

6 years ago
This helped my grade so much Perfect
wrote...

Yesterday
Thank you, thank you, thank you!
wrote...

2 hours ago
Smart ... Thanks!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1295 People Browsing
Related Images
  
 313
  
 302
  
 133
Your Opinion
Which is the best fuel for late night cramming?
Votes: 231