If three workers are assigned to a task lasting four days, two workers are assigned a task lasting three days, and one worker is assigned to a task lasting three days. The tasks can be completed independently of each other. If you are to schedule with a resource-limit, what is the minimum resource limit for the project?
 a. Three workers per day
  b. 21 worker-days
  c. Seven days
  d. Additional information is needed to determine the minimum number.
Read 76 times
1 Reply
Replies
Answer verified by a subject expert
lightingmcqueenlightingmcqueen
wrote...
Top Poster
Posts: 911
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

MADUBUCA76 Author
wrote...

6 years ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

Yesterday
Smart ... Thanks!
wrote...

2 hours ago
this is exactly what I needed
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  935 People Browsing
Related Images
  
 276
  
 565
  
 280
Your Opinion
What's your favorite funny biology word?
Votes: 334

Previous poll results: What's your favorite math subject?