The earliest start time for an activity is
 a. the date that all the resources for the project are available.
  b. calculated using the project start time and the estimated duration of all of its preceding activities.
  c. cannot be earlier than estimated, even if some activities are accelerated.
  d. should not be delayed or would cause the project to be delayed.
Read 56 times
1 Reply
Replies
Answer verified by a subject expert
jgfndjgfnd
wrote...
Top Poster
Posts: 871
Rep: 1 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

ovx1267 Author
wrote...

6 years ago
Thanks for your help!!
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Thank you, thank you, thank you!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  881 People Browsing
Related Images
  
 1107
  
 183
  
 879