In network planning, when three time estimates are used for each activity, it is assumed that the three estimates follow a ____ probability distribution.
 a. bell
  b. beta
  c. random
  d. normal
Read 32 times
1 Reply
Replies
Answer verified by a subject expert
kallierfkallierf
wrote...
Top Poster
Posts: 906
Rep: 6 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Hummer Author
wrote...

6 years ago
Thanks
wrote...

Yesterday
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

2 hours ago
Thanks
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  887 People Browsing
Related Images
  
 90
  
 521
  
 361
Your Opinion
Which country would you like to visit for its food?
Votes: 215