As the project progresses, the actual finish times (AFs) of completed activities will determine
 a. the earliest start and earliest finish times for the remaining activities in the network diagram, as well as the total slack.
  b. the earliest start and earliest finish times for the completed activities in the network diagram, as well as the total slack.
  c. the latest start and latest finish times for the remaining activities in the network diagram, as well as the total slack.
  d. the latest start and latest finish times for the completed activities in the network diagram, as well as the total slack.
Read 27 times
1 Reply
Replies
Answer verified by a subject expert
lightingmcqueenlightingmcqueen
wrote...
Top Poster
Posts: 911
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Micky5490! Author
wrote...

6 years ago
Thanks for your help!!
wrote...

Yesterday
Helped a lot
wrote...

2 hours ago
Smart ... Thanks!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1251 People Browsing
Related Images
  
 43
  
 412
  
 145
Your Opinion
Which of the following is the best resource to supplement your studies:
Votes: 292