Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.
 a. day 5
  b. day 3
  c. day 1
  d. Cannot be calculated based upon information given.
Read 49 times
1 Reply

Related Topics

Replies
su
wrote...
6 years ago
b