The fourth phase of the project life cycle involves ________.
 
  A) developing the initial ideas of what needs to be done
  B) conducting studies of factors that drive costs and productivity
  C) obtaining workers and equipment to execute plans
  D) training personnel that work in the new assembly unit
  E) preparing a schedule and a design for the assembly process

Question 2

A(n) ________ is a project planning tool which lists the tasks, key resources needed, completion deadlines, and the persons responsible for task completion.
 
  A) work breakdown structure
  B) network technique
  C) work plan
  D) Gantt chart
  E) bar chart

Question 3

A ________ is simply a plan for performing work or specifying the expected sequence of activities.
 
  A) schedule
  B) utility model
  C) directive style
  D) bar chart
  E) heuristic

Question 4

A(n) ________ is a visual illustration of the sequential relationships between work tasks, as well as the estimates for task completion times.
 
  A) action plan
  B) schedule
  C) utility model
  D) bar chart
  E) work breakdown structure

Question 5

________ take the basic information from the action plan and apply mathematical models to the data, which increases planning precision.
 
  A) Work plans
  B) Bar charts
  C) Network techniques
  D) Schedules
  E) Flow diagrams

Question 6

Which of the following is true about network techniques?
 
  A) They are used specifically to identify discrete steps in a process.
  B) They list project deadlines and the persons responsible for tasks.
  C) They mathematically compare decision alternatives with known desirable attributes.
  D) They are used to conduct what if analyses.
  E) They help in lowering the risk of cost overruns.

Question 7

________ are also called activity network diagrams or activity precedence diagrams.
 
  A) Computer-aided planning tools
  B) PERT charts
  C) Action plans
  D) Flow diagrams
  E) Utility models
Read 81 times
2 Replies
Replies
Answer verified by a subject expert
kiavashkiavash
wrote...
Posts: 354
Rep: 1 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Azhan Author
wrote...
6 years ago
Electric Light Bulb All of these are right, thanks!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  974 People Browsing
Related Images
  
 657
  
 100
  
 292
Your Opinion
What percentage of nature vs. nurture dictates human intelligence?
Votes: 436

Previous poll results: Do you believe in global warming?