Louie928 Louie928
wrote...
Posts: 1740
8 years ago
The project described in the table uses the same resource for activities A, B, C, and D. Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration?

Activity   Duration   Predecessor   WBS ID
W   4   --   12
A   3   W   16
B   4   W   15
C   5   W   13
D   6   W   14
E   1   B   17
Z   7   A, E, C, D   18

A) Activity A
B) Activity B
C) Activity C
D) Activity D
Textbook 
Project Management: Achieving Competitive Advantage

Project Management: Achieving Competitive Advantage


Edition: 4th
Author:
Read 226 times
3 Replies
Yuppp
Replies
Answer verified by a subject expert
flammableflammable
wrote...
Top Poster
Posts: 1729
8 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

Louie928 Author
wrote...
8 years ago
Thank you again
Yuppp
wrote...
8 years ago
Good luck with the rest, Louie928
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  839 People Browsing
Related Images
  
 276
  
 312
  
 365
Your Opinion
Who will win the 2024 president election?
Votes: 119
Closes: November 4

Previous poll results: What's your favorite math subject?