The project described in the table uses the same resource for activities A, B, C, and D. Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration?

Activity   Duration   Predecessor   WBS ID
W   4   --   12
A   3   W   16
B   4   W   15
C   5   W   13
D   6   W   14
E   1   B   17
Z   7   A, E, C, D   18

A) Activity A
B) Activity B
C) Activity C
D) Activity D
Textbook 
Project Management: Achieving Competitive Advantage

Project Management: Achieving Competitive Advantage


Edition: 4th
Author:
Read 262 times
3 Replies
Yuppp
Replies
Answer verified by a subject expert
flammableflammable
wrote...
Top Poster
Posts: 1730
9 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

Louie928 Author
wrote...
9 years ago
Thank you again
Yuppp
wrote...
9 years ago
Good luck with the rest, Louie928
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  2183 People Browsing
Related Images
  
 308
  
 243
  
 426
Your Opinion
Do you believe in global warming?
Votes: 782