The project described in the table uses the same resource for activities A, B, C, and D.
 
  Which activity gets first use of this resource if we assign the resource based on the activity with the smallest amount of slack?
 
  Activity Duration Predecessor WBS ID
  W 4 -- 12
  A 3 W 16
  B 4 W 15
  C 5 W 13
  D 6 W 14
  E 1 B 17
  Z 7 A, E, C, D 18
  A) Activity A
  B) Activity B
  C) Activity C
  D) Activity D
Read 68 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
D