Very short work packages would be better managed by:
A) The caveat emptor rule.
B) The prior knowledge rule.
C) The 0/100 rule.
D) The percentage complete rule.
Textbook 
Project Management: Achieving Competitive Advantage

Project Management: Achieving Competitive Advantage


Edition: 4th
Author:
Read 665 times
4 Replies
Yuppp
Replies
Answer verified by a subject expert
flammableflammable
wrote...
Top Poster
Posts: 1729
8 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

Louie928 Author
wrote...
8 years ago
Right on time! Thank you for the help
Yuppp
wrote...
8 years ago
Excellent! Have a Merry Christmas Slight Smile
wrote...
3 years ago
thank you.
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  858 People Browsing
Related Images
  
 2104
  
 366
  
 298
Your Opinion