The heir to the throne was due 60 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery.
 
  The seven activities, their normal and expedited times (in days) and costs appear in the table. Just to be on the safe side, he decided to bring the project in at 53 days in case the delivery was a week early. Tell him what the least expensive 53-day project is; which activities should be reduced in duration, by how many days, and at the total cost, so he can roll up the sleeves on his World's Greatest Dad sweatshirt, and get to work.
 
  Activity Normal time Crash time Normal Cost Crash Cost Predecessor
  A 5 3 500 1100
  B 18 15 900 2300 A
  C 12 9 2500 3000 A
  D 9 7 500 650 B
  E 15 12 3000 5000 B
  F 12 10 4000 5000 C, D
  G 20 15 3600 4800 E, F
Read 25 times
2 Replies

Related Topics

Replies
wrote...
6 years ago
The project before any expediting takes 64 days. The activities that should be expedited are D, for 2 days at 75/day; G for 5 days at 240/days; and A for 2 days at 300/day, and B for 2 days at 466.67/day. The total cost to expedite is 2,883.33 in addition to the normal cost of 15,000, for a total tab of 17,883.33 plus a lifetime of disappointment and shame.
BoyzGonWild Author
wrote...
6 years ago
A++++++
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1132 People Browsing
Related Images
  
 447
  
 1357
  
 4838
Your Opinion
Who will win the 2024 president election?
Votes: 19
Closes: November 4

Previous poll results: Who's your favorite biologist?