A change in the estimated duration of any activity on that path will cause a corresponding change in the slack for that path.
 a. True
  b. False
  Indicate whether the statement is true or false
Read 49 times
1 Reply
Replies
Answer verified by a subject expert
rcollins105rcollins105
wrote...
Top Poster
Posts: 914
Rep: 6 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Chinnab Author
wrote...

6 years ago
Helped a lot
wrote...

Yesterday
You make an excellent tutor!
wrote...

2 hours ago
This helped my grade so much Perfect
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1257 People Browsing
Related Images
  
 237
  
 296
  
 251
Your Opinion
What's your favorite coffee beverage?
Votes: 274