A project consists of four activities with information as shown in the table. What is the overall standard deviation of the project's duration?
 
  Activity Predecessor Length Standard Deviation
  A -- 10 2
  B A 12 3
  C A 16 2
  D B, C 14 3
 
  A) 6.2
  B) 4.1
  C) 2.8
  D) 5.1
Read 42 times
1 Reply
- - UCLA Student

Related Topics

Replies
wrote...
6 years ago
B