If the total slack for a project is 4 days, this means
 a. the activities on the path can be delayed a total of four days and the project still could be completed on time.
  b. the activities on the path must be accelerated by four days for the project to be completed on time.
  c. all the activities must be accelerated by four days for the project to be completed on time.
  d. all the activities can be delayed by four days and the project still be completed on time.
Read 49 times
1 Reply
Replies
Answer verified by a subject expert
vulshafer15vulshafer15
wrote...
Top Poster
Posts: 889
Rep: 1 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

abbiedigings Author
wrote...

6 years ago
This site is awesome
wrote...

Yesterday
This calls for a celebration Person Raising Both Hands in Celebration
wrote...

2 hours ago
this is exactly what I needed
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  869 People Browsing
Related Images
  
 1004
  
 2534
  
 355
Your Opinion
Who will win the 2024 president election?
Votes: 19
Closes: November 4

Previous poll results: Do you believe in global warming?