Schedule control involves four steps. List the four steps in order.
Read 46 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
Schedule control involves four steps:
1 . Analyzing the schedule to determine which areas may need corrective action
2 . Deciding what specific corrective actions should be taken
3 . Revising the plan to incorporate the chosen corrective actions
4 . Recalculating the schedule to evaluate the effects of the planned corrective actions