× Didn't find what you were looking for? Ask a question
Top Posters
Since Sunday
r
4
L
4
3
d
3
M
3
l
3
V
3
s
3
d
3
a
3
g
3
j
3
New Topic  
mjhgfd mjhgfd
wrote...
6 years ago
Schedule control involves four steps. List the four steps in order.
Read 57 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
Schedule control involves four steps:
1 . Analyzing the schedule to determine which areas may need corrective action
2 . Deciding what specific corrective actions should be taken
3 . Revising the plan to incorporate the chosen corrective actions
4 . Recalculating the schedule to evaluate the effects of the planned corrective actions
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1716 People Browsing
Related Images
  
 775
  
 178
  
 346
Your Opinion