The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have?
 a. Negative 5 days slack.
  b. Positive 5 days slack.
  c. Positive 17 days slack.
  d. Positive 3 days slack.
Read 68 times
1 Reply
Replies
Answer verified by a subject expert
sky2walkersky2walker
wrote...
Top Poster
Posts: 957
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Cynh972 Author
wrote...

6 years ago
This site is awesome
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Correct Slight Smile TY
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  737 People Browsing
 123 Signed Up Today
Related Images
  
 523
  
 1638
  
 316
Your Opinion
What percentage of nature vs. nurture dictates human intelligence?
Votes: 432