Posts: 959
Rep: 0 0
6 years ago
If a load report (resource requirements profile) shows a work center scheduled beyond capacity:
A) the company must add capacity by enlarging the facility.
B) the company must add capacity by such tactics as overtime and subcontracting.
C) the Wagner-Whitin algorithm should be used to rebalance the load.
D) the work center's load may be smoothed by such tactics as operations splitting or lot splitting.
E) the aggregate plan must be revised.
Textbook 
Operations Management

Operations Management


Edition: 10th
Authors:
Read 64 times
1 Reply
Replies
Answer verified by a subject expert
kadajikadaji
wrote...
Top Poster
Posts: 992
Rep: 9 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

retownes Author
wrote...

6 years ago
You make an excellent tutor!
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Helped a lot
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1248 People Browsing
Related Images
  
 2087
  
 363
  
 10262