Lead time for cakes is 2 days with daily demand of 10 cakes and a safety stock of ½ a day. Each container (kanban) holds 1 cake. What is the correct number of kanbans?
A) 5
B) 1
C) 4
D) 25
E) 10
Textbook 
Operations Management

Operations Management


Edition: 10th
Authors:
Read 278 times
2 Replies
Replies
Answer verified by a subject expert
HplyEvrAftrHplyEvrAftr
wrote...
Top Poster
Posts: 1033
6 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

Apatix Author
wrote...
6 years ago
I hope they pay you for the awesome work you do around here.

Thank you
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1289 People Browsing
Related Images
  
 173
  
 719
  
 310
Your Opinion
Who will win the 2024 president election?
Votes: 3
Closes: November 4

Previous poll results: Who's your favorite biologist?