If three workers are assigned to a task lasting four days, two workers are assigned a task lasting three days, and one worker is assigned to a task lasting three days. The tasks can be completed independently of each other. If you are to schedule with a resource-limit, what is the minimum resource limit for the project?
 a. Three workers per day
  b. 21 worker-days
  c. Seven days
  d. Additional information is needed to determine the minimum number.
Read 75 times
1 Reply
Replies
Answer verified by a subject expert
lightingmcqueenlightingmcqueen
wrote...
Top Poster
Posts: 911
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

MADUBUCA76 Author
wrote...

6 years ago
You make an excellent tutor!
wrote...

Yesterday
Just got PERFECT on my quiz
wrote...

2 hours ago
This helped my grade so much Perfect
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  873 People Browsing
Related Images
  
 72
  
 61
  
 852
Your Opinion
Where do you get your textbooks?
Votes: 372